At the end of 6th Semester,we
students at Amity University, Noida were supposed to complete
Summer Internship as proposed in the curriculum.I had joined RITES Ltd.(Rail
India Technical and Economic Services-A Govt. of India Enterprise) along with
Mohd. Umar and Nilay Vats (my batch mates).Duration of the Summer Internship
was around 6 weeks.It was overall a good learning experience.
The Project is located within the
campus of Jamia Millia Islamia,New Delhi.The project involved construction
of Hostel Accommodation for Boys/Girls in the University.The
Project cost was roughly estimated out to be around 10 crores.RITES was holding
the responsibility of PMC(Project Management Consultants) and the Construction
was being carried out by 2 Contractors.The duration of the project was roughly
1-1.5 years.We were guided by both faculty guides as well as Industry guides
who assisted us in every possible way.My Faculty Guide on behalf of Amity is
Ms. Madhuri Kumari and my Industry guide on behalf of RITES was Mr. Mansoor.
Both of them made my work easier and their guidance was very much helpful.
During the 1st week of the visit we
were made to do some calculations based on what we have learnt in college.We
were handed over the Plan/Drawings of the Project so that we could get a rough
idea on what we are working on.The Next step involved was calculation of Carpet
Area,Wall Area etc. by looking into the drawings.We were also introduced to
various employees of RITES.Also we were taken to the Construction Site to
observe the Area.When we reached the site we noticed that Site Layout/Levelling
was being carried out. Levelling was being carried out with the help
of a device called Dumpi Level.This process was completed within 2 days.Next
up,the Layout was executed which involved marking of Boundary of area which is
to be excavated.Layout is the marking up of all the essential
boundaries so that excavation may be done.This was executed with as much
perfection as possible as thew slightest mistake could have delayed/ruined the
project.
The next 10 days
were utilized taken up by workers for full Excavation of Site.The
delay was due to some mismanagement.After the excavation it was time to level
the ground as well as to give it a good finish.This was again accomplished with
help of Dumpi level.Then,it was time for application of PCC(Plain Cement
Concrete).PCC is a thin layer of Concrete that is applied on the base of the
Foundation on which the Raft Foundation is to be laid out.The PCC was made in
ratio of 1:4:8.Its important to mention that a lot of difficulties were faced
during this stage as the concrete quality should have been upto the standards
After PCC was
applied the next stage was Curing of PCC.Curing is the process of maintaining
adequate moisture content so that concrete hardens.After curing,Layout of
Columns was done with the help of Total Station.The Columns were of size
650mm*350mm. The raft foundation was laid out over the PCC(after the
layout) with a clear cover.The Raft Foundation/Mat was of 16mm diameter.
For the extra bars that were provided we had to look up in the Structural
Drawings so as to make sure that construction is accurate and so that load is
distributed properly and also so that the structure does not fail.
And so with the
completion of Raft/extra bars the next process was positioning of the columns
reinforcement.The Column reinforcement was erected properly along with proper
positioning of Stirrups.The main process after this was Shuttering of both the
Raft as well as Columns and mass concreting of both of them in
a monolithic fashion.This process was quite frustrating and tough as it
involved perfect timing,experience as well as harsh working hours as Concreting
couldnt be done in day during which temperatures would reach 45 degrees.
This step was a
milestone in the project as now the next steps were relatively easier.I
would also like to mention that during this entire processes RITES was ensuring
that the project was according to Indian Standards as well as stable and safe.
Backfilling is the next stage which involved filling the
excavated area with excavated soil.Compaction was also done with help of
rollers so that soil strength is restored to normal as much as possible.
Along with the
Construction techniques we were also shared with information on Project
Management as well as with Bill of Quantities.Office involved lots of paperwork
and formalities.Thus overall my Internship was quite a big success as i was
introduced to lots of things which i was not aware of.It gave me confidence in
the field of Civil Engineering and I hope to gain more Knowledge in various
other Civil Engineering Projects.
Ashutosh Pant
7CE-2
A2325110005
B.Tech-Civl+MBA
No comments:
Post a Comment